Spans the Arthur Kill.

"In 2003, The Port Authority of New York and New Jersey began construction on the Goethals Bridge Deck Rehabilitation Project. The significant work on the New Jersey-bound roadway was completed in November 2005, when full westbound roadway closures were suspended. On March 6, 2006, rehabilitation work began on the New York-bound roadway. Work in the New York-bound direction will be suspended for the winter in November, 2006, and resume in the spring of 2007. The project is expected to be complete by mid-2007."

For more facts, visit the Port Authority of New York and New Jersey Goethals Bridge page